How Washington Really Works, F-22 Edition

Belatedly: A striking admission from last week's WashPost feature on the troubled F-22 fighter program, currently the subject of an impending showdown between Congress and the Obama White House.

Designed during the early 1980s to ensure long-term American military dominance of the skies, the F-22 was conceived to win dogfights with advanced Soviet fighters that Russia is still trying to develop....

Its troubles have been detailed in dozens of Government Accountability Office reports and Pentagon audits. But Pierre Sprey, a key designer in the 1970s and 1980s of the F-16 and A-10 warplanes, said that from the beginning, the Air Force designed it to be "too big to fail, that is, to be cancellation-proof."

Lockheed farmed out more than 1,000 subcontracts to vendors in more than 40 states, and Sprey -- now a prominent critic of the plane -- said that by the time skeptics "could point out the failed tests, the combat flaws, and the exploding costs, most congressmen were already defending their subcontractors' " revenues.

John Hamre, the Pentagon's comptroller from 1993 to 1997, says the department approved the plane with a budget it knew was too low because projecting the real costs would have been politically unpalatable on Capitol Hill.

"We knew that the F-22 was going to cost more than the Air Force thought it was going to cost and we budgeted the lower number, and I was there," Hamre told the Senate Armed Services Committee in April. "I'm not proud of it," Hamre added in a recent interview.

--Michael Crowley